Dam collapses in Brazil: mud sludge leaves over 200 miners missing

Saturday, January 26th 2019 - 07:50 UTC
Full article 3 comments
Seven bodies had been recovered, said Avimar de Melo Barcelos, mayor of the town of Brumadinho where the dam burst in the state of Minas Gerais Seven bodies had been recovered, said Avimar de Melo Barcelos, mayor of the town of Brumadinho where the dam burst in the state of Minas Gerais
Vale Chief Executive Fabio Schvartsman said only one-third of the roughly 300 workers at the site had been accounted for Vale Chief Executive Fabio Schvartsman said only one-third of the roughly 300 workers at the site had been accounted for
Television showed a vast swathe of thick red mud scarring the verdant hills below the mine, cutting through farms and residential areas leveling everything Television showed a vast swathe of thick red mud scarring the verdant hills below the mine, cutting through farms and residential areas leveling everything

Brazilian rescuers were searching for some 200 missing people after a tailings dam burst on Friday at an iron ore mine owned by Vale SA, the second major dam disaster involving the company in just over three years.

Seven bodies had been recovered by nightfall, said Avimar de Melo Barcelos, the mayor of the town of Brumadinho where the dam burst in the mining-heavy state of Minas Gerais. The toll was expected to rise sharply.

Vale Chief Executive Fabio Schvartsman said only one-third of the roughly 300 workers at the site had been accounted for. He said a torrent of sludge tore through the mine's offices, including a cafeteria during lunchtime.

Minas Gerais is still recovering from the collapse in November 2015 of a larger dam that killed 19 people in Brazil's worst environmental disaster. That dam, owned by the Samarco Mineracao SA joint venture between Vale and BHP Billiton, buried a village and poured toxic waste into a major river.

Schvartsman said the dam that burst on Friday at the Feijao iron mine was being decommissioned and had a capacity of 12 million cubic meters – a fraction of the roughly 60 million cubic meters of toxic waste released by the Samarco dam break.

“The environmental impact should be much less, but the human tragedy is horrible,” he told journalists at Vale's offices in Rio de Janeiro. He said equipment had shown the dam was stable on Jan. 10 and it was too soon to say why it collapsed.

Television footage showed a vast swathe of thick red mud scarring the verdant hills below the mine, cutting through farms and residential areas and leveling everything in its wake.

Fire brigade spokesman Lieutenant Pedro Aihara said the torrent of mud stopped just short of the local Paraopeba river, a tributary of Brazil's longest river, the Sao Francisco.

“Our main worry now is to quickly find out where the missing people are,” Aihara said on GloboNews cable television channel. Scores of people were trapped in nearby areas flooded by the river of sludge released by the dam failure.

Helicopters plucked people covered in mud from the disaster area, including a woman with a fractured hip who was among eight injured people taken to hospital, officials said.

The Inhotim Institute, a world-famous outdoor contemporary art museum a few miles from downtown Brumadinho, evacuated visitors and closed its doors out of precaution.

The Feijao mine is one of four in Vale's Paraoeba complex, which includes two processing plants and produced 26 million tons of iron ore in 2017, or about 7% of Vale's total output, according to information on the company's website. Feijao alone produced 7.8 million tons of ore in 2017.

Brazil's recently inaugurated President Jair Bolsonaro dispatched three ministers to survey the disaster area and will visit himself on Saturday, his chief spokesman said.

Former environmental minister and presidential candidate Marina Silva said Brazilian authorities and private miners had not learned anything from the 2015 Samarco disaster near the city of Mariana and called it unacceptable.

Operations at Samarco remain halted over new licensing, while the companies have worked to pay damages out of court, including an agreement that quashed a 20 billion reais (US$5.31 billion) civil lawsuit last year. Federal prosecutors suspended but have still not closed an even larger lawsuit.

“Three years after the serious environmental crime in Mariana, with investigations still ongoing and no one punished, history repeats itself as tragedy in Brumadinho,” Silva said on Twitter.

 

Categories: Environment, Politics, Brazil.

Top Comments

Disclaimer & comment rules
Read all comments

Commenting for this story is now closed.
If you have a Facebook account, become a fan and comment on our Facebook Page!